KAST Construction is the top-ranked builder for the Village Hall, police headquarters and Miami-Dade Fire Station 27 on the 79th Street Causeway. Here is everything residents need to know.
North Bay Village is closer than ever to building a permanent home for its government. At its October 20, 2026 meeting, the Village Commission took up a resolution awarding construction of the new North Bay Village Hall/Public Safety Complex and Miami-Dade County Fire Station No. 27 to KAST Construction Company Florida, LLC. The total authorization is capped at $50,855,570.49.
The complex will rise on Village-owned land at 1335 79th Street Causeway on Harbor Island. It will put the Village’s administrative offices, Commission chambers, police station and a new county fire-rescue station under one roof, with parking on site. It is one of the largest public building projects in the Village’s history.
What the New North Bay Village Hall Will Look Like
Renderings in KAST’s October 2026 presentation show a modern mid-rise building on the corner of the 79th Street Causeway, with Biscayne Bay behind it. The building is wrapped in a light silver, perforated metal screen facade broken by long horizontal bands of windows. Large “NBV” letters stand out on the causeway side, above a glass-walled ground floor. A wide staircase leads to the corner entrance, framed by palm trees and landscaping.
The building was designed by Wannemacher Jensen Architects, hired by the Commission in March 2023 (Resolution No. 2023-045). The renderings are illustrations from the contractor’s proposal; the final look follows the architect’s approved permit drawings.
Inside, the complex will include:
- Village Hall: administrative offices and new Commission chambers.
- Police headquarters: a modern station for the North Bay Village Police Department, with security windows.
- Miami-Dade Fire Rescue Station 27: an apparatus bay with large four-fold exterior doors and a decontamination area for firefighters.
- Resilient building systems: a standby emergency generator, fire pumps, elevators and electric-vehicle charging stations.
The structure will sit on auger-cast grout piles with post-tensioned concrete floors, a common approach for heavy buildings on South Florida’s bayfront soils.
How Much the New Village Hall Costs
KAST’s Guaranteed Maximum Price (GMP) is $48,778,723. With alternates, allowances and an owner’s contingency, the maximum authorization reaches $50,855,570.49:
| Item | Amount |
|---|---|
| Guaranteed Maximum Price (GMP) | $48,778,723.00 |
| Alternates (additions to the base scope) | $76,847.49 |
| Allowances (permits and fees, special inspections, audiovisual systems, traffic-signal preemption) | $500,000.00 |
| Owner’s contingency (unforeseen conditions) | $1,500,000.00 |
| Total maximum authorization | $50,855,570.49 |
The allowances and contingency are spent only if needed, with Village review. The resolution lets the Village Manager approve change orders within the $50.9 million cap. Anything above it must go back to the Commission.
Who pays for it
The Village has identified $50,046,502 in funding, according to the Finance Department:
- $38,334,284 in developer contributions already received
- $7,425,000 from Miami-Dade County for the fire station, paid in phases
- $4,287,218 in Village Hall General Obligation Bond (GOB) proceeds
Another $682,000 in developer money is expected once an amended El-Ad development agreement is approved. The FY 2026-2027 budget sets aside $24,378,991 for the project, with the rest to be spent in later years as construction moves forward.
The identified funds sit about $809,000 below the full authorization, or about $127,000 below it with the El-Ad money. Because the contingency and allowances are only drawn as needed, the Finance Department states that total funding is available.
Why KAST Construction Was Chosen Over the Lowest Bid
The contractor was picked in a two-phase competition. In July 2025, the Village issued Request for Qualifications No. 2025-006 and received packages from ten firms. In October 2025, the Commission short-listed five: CORE Construction, Gulf Building, James P. Pirtle Construction, KAST Construction and West Construction.
Only three of the five submitted price proposals, opened on September 16, 2026:
| Firm | Proposed price (GMP) | Final rank |
|---|---|---|
| KAST Construction Company Florida, LLC | $48,778,723 | 1 |
| CORE Construction Services of Florida, LLC | $56,110,204 | 2 |
| Gulf Building Corporation | $44,999,107 | 3 |
Price was not the only factor. The Evaluation Committee also scored each firm’s Master Project Approach Plan and an oral presentation, held on October 6, 2026. KAST finished first even though its price is about $3.78 million higher than Gulf Building’s. If the Village cannot reach a contract with KAST, the resolution lets the Manager negotiate with the next-ranked firm.
In its presentation, KAST described itself as the largest construction-manager-at-risk contractor in Miami-Dade County. It said its team has completed 58 projects worth $3.34 billion for Miami-Dade Fire Rescue and county government. It also cited past work with the project architect on a fire station prototype for Palm Beach County. KAST committed to $500,000 in savings through direct purchase of about $8 million in materials and equipment, and offered a three-year warranty.
When Will the New Village Hall Open?
KAST’s proposed schedule puts substantial completion on November 8, 2028 and final completion on December 23, 2028. The key milestones:
- Fall 2026: The Village’s separate sitework contractor begins site preparation; Commission approval and contract negotiations follow.
- January 2027: GMP contract signed and notice to proceed issued to KAST.
- January-April 2027: Preconstruction review, value engineering and dewatering permits.
- March 2027: KAST’s construction start date.
- June-December 2027: Foundations and the building’s concrete structure.
- November 2027-August 2028: Exterior walls, windows and roof.
- December 2027-November 2028: Interior build-out and start-up of major systems.
- Late 2028: Final inspections and handover.
These dates come from the contractor’s proposal and may shift once the contract is signed.
What It Means for North Bay Village Residents
The project has been a long time coming. Village voters approved general obligation bonds for a combined Village Hall and public safety complex in January 2008, when its cost was estimated at about $20 million. Since then, Miami-Dade County records show Fire Station 27 moving from its original building to a temporary station, while Village offices have worked out of 1666 Kennedy Causeway.
When it opens, the complex will give the police department and Miami-Dade Fire Rescue modern, storm-ready facilities on the island they serve. Residents will also gain a permanent civic home for Commission meetings and Village services. Most of the bill is covered by contributions from private developers rather than new Village appropriations.
northbayvillage.news will keep following the contract, the groundbreaking and each stage of construction.
Frequently Asked Questions
Where will the new North Bay Village Hall be built? At 1335 79th Street Causeway on Harbor Island, on land the Village owns.
How much will the new Village Hall cost? The guaranteed maximum construction price is $48,778,723. The total authorization, including contingency, allowances and alternates, is up to $50,855,570.49.
Who is building it? KAST Construction Company Florida, LLC, ranked first by the Village’s Evaluation Committee. The architect is Wannemacher Jensen Architects.
What will be inside? Village administrative offices, Commission chambers, the police station, Miami-Dade Fire Rescue Station 27 and parking.
When will it be finished? The contractor’s schedule targets substantial completion in November 2028.
How is it being paid for? The Village says the project is funded by developer contributions, Miami-Dade County’s fire station payments and existing General Obligation Bond proceeds, with no new appropriation needed this fiscal year.
North Bay Village is taking a big step toward its future. The new Village Hall and Public Safety Complex will rise at 1335 79th Street Causeway on Harbor Island. It will bring Village offices, new Commission chambers, a modern police headquarters and Miami-Dade Fire Rescue Station 27 together in one building. KAST Construction was chosen in a competitive process, and the project is backed by more than $50 million in identified funding. Most of that comes from private developer contributions, with additional support from Miami-Dade County and voter-approved bonds. Construction is set to start in 2027, with completion targeted for late 2028. The result will be a permanent civic home for residents and stronger, storm-ready facilities for the police officers and firefighters who serve them. The complex is a clear sign of the growth and momentum building across North Bay Village.